Authenticated is false

Candela

city

Candela

40 Upper Heidelberg Road, IVANHOE, 3079

Anticipated Completion September 2026

November 2025

Dear Candela Community,

We’re pleased to share the latest construction update from Candela Ivanhoe, where your future homes are progressing well. Each milestone brings us one step closer to welcoming our new community to this exceptional address.

Construction is 45% complete as at 31 October 2025.

Construction highlights include:

  • Basement level 1 formwork stripped, backpropping removed, blockwork constructed and services rough-in underway
  • Ground floor formwork fully stripped and backpropping removed
  • Ground floor setout of walls underway in preparation for framing, services rough-in and window installation about to commence
  • Level 1 formwork fully stripped and backpropped
  • Level 2 and 3 concrete pours complete and precast walls and columns erected
  • Level 4 formwork erected


We will continue to share monthly updates as construction advances.

Thank you once again for your trust and support as we bring the Candela project to life.

Kind regards,
The Candela Design Team

person